Judge Baratha Chakravarthy / I agree with the Learned Counsel for the Workman that the delay will impact the Workman. However, I cannot undertake the exercise myself in this case due to the complexity of the charges, which involve many factual aspects, and the 103 documents marked on behalf of the respondent Management by consent that must be considered. Therefore, I cannot uphold the award of the first respondent authority
by Sekar Reporter · Published March 10, 2026
-
THE HONOURABLE Ms. JUSTICE P.T. ASHA O.P.No.549 of 2019 & A.No.4849 of 2019 M/s.Resurgent Power Projects Limited–Jurisdiction under Section 34 of the Arbitration and Conciliation Act, does not find any ground for interference. The Original Petition stands dismissed.