Dam case THE HON-BLE MR.MUNISHWAR NATH BHANDARI, ACTING CHIEF JUSTICE AND THE HON-BLE MR.JUSTICE P.D.AUDIKESAVALU W.P.No.27183 of 2021 -Mr.P.Muthukumar State Government Pleader for respondents 1 to 5

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED: 17.12.2021

CORAM :

THE HON-BLE MR.MUNISHWAR NATH BHANDARI,
ACTING CHIEF JUSTICE
AND
THE HON-BLE MR.JUSTICE P.D.AUDIKESAVALU

W.P.No.27183 of 2021

S.Rathinavel .. Petitioner

Vs

1.The District Collector,
Erode District.

2.The Superintendent of Police,
Erode District.

3.The Assistant Director,
Rural Development,
Erode District.

4.The Chairman,
Gobichettipalayam Panchayat Union,
Gobichettipalayam,
Erode District.

5.The Block Development Officer,
Gobichettipalayam,
Erode District. .. Respondents

Prayer: Petition filed under Article 226 of the Constitution of India praying for a writ of mandamus directing the respondents 1 to 5 to take suitable legal action to protect the Check Dam construction at Sellamuthunagar Stream (Odai) under Mahatma Gandhi NREGA Scheme, Kottupulloampalayam Panchayat, Gobichettipalayam Taluk, Erode District.

For the Petitioner

:
Mr.L.P.Shanmugasundaram

For the Respondents
:
Mr.P.Muthukumar
State Government Pleader
for respondents 1 to 5

ORDER
(Order of the Court was made by
the Hon-ble Acting Chief Justice)

This writ petition has been filed by the petitioner to protect the Check Dam constructed at Sellamuthunagar Stream (Odai) under Mahatma Gandhi NREGA Scheme, Kottupullampalayam Panchayat, Gobichettipalayam Taluk, Erode District.

2. A representation to protect the Check Dam was made by the petitioner on December 10, 2021 and soon thereafter, the writ petition was filed on December 15, 2021. In any case, the Check Dam in question is to be protected, for which no objection has been raised by learned Government Pleader appearing for the respondents.

3. Accordingly, the writ petition is disposed of with a direction to the respondents to undertake adequate repair work to protect the Check Dam as some damage seems to have caused and is also visible from the photographs produced along with the writ petition. The repair work is directed to be completed within a period of three months from the date of receipt of a copy of this order. No costs. W.M.P.No.28676 of 2021 is closed.

(M.N.B., ACJ) (P.D.A., J.)
17.12.2021
Index : No
bbr

To:

1.The District Collector,
Erode District.

2.The Superintendent of Police,
Erode District.

3.The Assistant Director,
Rural Development,
Erode District.

4.The Chairman,
Gobichettipalayam Panchayat Union,
Gobichettipalayam,
Erode District.

5.The Block Development Officer,
Gobichettipalayam,
Erode District.

M.N.BHANDARI, ACJ
AND
P.D.AUDIKESAVALU,J.

bbr

W.P.No.27183 of 2021

17.12.2021