Justice M. Sundar ordered notice to the consortium after Advocate-General Vijay Narayan, representing CMRL, claimed the award passed by the tribunal, comprising three technical members, was per se illegal and unintelligible because adequate reasons had not been assigned for passing such an award by a 2-1 majority.

15

NEWS CITIES CHENNAI
CHENNAI
CMRL moves High Court against tribunal’s award of ₹39.97 crore
St.Thomas Mount Metro station
St.Thomas Mount Metro station | Photo Credit: G_KRISHNASWAMY ;G_KRISHNASWAMY
Legal Correspondent
CHENNAI 03 FEBRUARY 2021 00:06 IST
UPDATED: 03 FEBRUARY 2021 00:06 IST

St. Thomas Mount station construction contract was terminated in 2014
Chennai Metro Rail Ltd. (CMRL) has approached the Madras High Court against an award passed by a tribunal last year directing it to pay ₹39.97 crore to Consolidated Constructions Consortium Ltd. whose contract for the construction of the St. Thomas Mount elevated station and the associated viaducts was terminated in 2014.

Justice M. Sundar ordered notice to the consortium after Advocate-General Vijay Narayan, representing CMRL, claimed the award passed by the tribunal, comprising three technical members, was per se illegal and unintelligible because adequate reasons had not been assigned for passing such an award by a 2-1 majority.

The A-G told the court that CMRL was a special purpose vehicle (SPV) floated for establishing metro rail in Chennai. The Centre as well as the State government had equal stakes in the SPV. On February 17, 2011, it awarded the contract to the consortium for an estimate of ₹78.61 crore.

Advertising

Advertising
Financial stress
As per the terms of the contract, the work should have been started on February 21, 2011, and completed by September 6, 2013. However, the consortium was able to complete only 40% of the work, despite being granted two extensions. The reason for the delay was a deep financial stress faced by the consortium, which owed about ₹900 crore to several banks.

“They [the consortium] realised that they were in a hopeless situation and therefore issued a notice of termination on January 2, 2014, and we terminated the contract on January 11, 2014. Thereafter, they raised an arbitration claim amount of ₹91.17 crore, and what was awarded was ₹39.97 crore,” the A-G said and urged the court to stay the operation of the award.

Advocate S.S. Rajesh blamed CMRL for the financial stress and said multiple arbitral proceedings were pending between it and the consortium. He said he would demonstrate, on the next date of hearing, how CMRL was liable to compensate the losses suffered by the consortium.

Comments
More In
ChennaiChennai
Previous Story
Two arrested for attacking policeman in Madhavaram
Next Story
Corporation to spruce up Anai Eri

 

 

LATEST NEWS

Investigation
Jammu And Kashmir
Rajasthan
Gujarat
USA
Vaccines
Uttar Pradesh
Punjab
Economy, Business And Finance
Madhya Pradesh
West Bengal
New Delhi
About Us Terms of Use Privacy Policy Contacts Archive Print Subscription ePaper Digital Subscription Rss Feeds Sitemap

You may also like...